Construction Of IG Unit
Project Status: Ongoing
OFFICE OF THE Nagar Palika Parshad, Khargone
Khargone (M.P.)
Construction of LIG 120 Unit Houses G+3 and type block houses and related development Including building Construton at Satya Vistar, the work as follows :- Sewerage line, water supply line, & internal electrifications works, etc.
a) Total Built – up Area : 12729.60 sqmtr. b) RCC Work M – 20 : 3692.20 cum. c) PCC Work M – 15 : 482.90 cum. d) Structural Steel : 608.53 MT. e) Excavation work : 4298.61 cum.